A single machine work center has five jobs assigned to it. They are labeled, in the order of their arrival in the shop, as jobs A, B, C, D and E….

Question 8Suppose SPT rule is being used in a “dynamic” scheduling problem. There are five jobs A,B,C,D, and E ready to be processed at the present time. The processing times for the five jobs are 1, 9, 7, 2, and 6 days respectively. A new job F will arrive on the 8th day. The processing time for job F is 5 days. On which day (from present time) job F will be completed?Answer